Since last year the specialists of the Litana group have been continuing the implementation of the project at the power station in the Finnish city of Vantaa. Currently, the installation of metal structures, equipment, pipelines, as well as electrical installation works are carried out at the industrial facility.

Project manager R. Kudriašov, summarizing the completed and upcoming works, notes: „Our team has already completed the main tasks for the installation of metal structures, wall panels and roofs. The pipeline systems are being tested to be handed over to the customer. The works continue on the installation of electrical equipment: laying of cable tracks, low-voltage cable, connection of temperature sensors, pressure sensors and gas analyzers.“

According to R. Kudriašov, the workload of the upcoming months will be very intensive, because the works at the facility are coming to an end: still to mount the production filters and to complete other previously started works by the end of May.